|
Facilities News for April, 2008
- Marine Research Building Complex
| Photos |
This project involves the demolition and replacement of three outdated laboratory buildings with a new research complex. This complex includes a new 71,000 square foot scientific research building and a 46,000 square foot seawater laboratory. W.M. Jordan started construction in August 2005. A final certificate of use and occupancy was issued for the Seawater Research Laboratory on April 2, 2007. VIMS began occupying Andrews Hall in December 2007. The contractor continues to work on repairing the punchlist deficiencies so that VIMS can apply for the final certificate of occupancy which will give VIMS unrestricted use of the building. Bullpen furniture for student and technician office space was installed and is ready to occupy soon.
- Field Support Center
| Floor Plan | Perspective |
The project involves the construction of a 10,000 square foot facility located at the Gloucester Point Campus. This facility will replace the current vessel operation's facilities and field support infrastructure which was severely damaged as a result of Hurricane Isabel. A construction firm has been contracted to provide pre-construction services. The project is scheduled for completion in early 2009.
- Improve Information Technology Infrastructure
I Photo I
The project involves the modernizing of VIMS' aging information technology infrastructure to meet increasing demands for information exchange including systems to carry voice, data, and video. The Gloucester Point campus is vulnerable to lightning strikes and this project has completely replaced the original copper network with new high speed fiber optics to prevent damage to expensive and sensitive network hardware. Distance learning capabilities have been completed for the Gloucester Point and Wachapreague campuses. Construction to improve the air conditioning and power requirements for the Watermen's Hall network server room was completed. New servers were purchased. Along with networking Andrews Hall and the Seawater Research Laboratory, VIMS will extend 24x7 networking capability to existing campus buildings, such as Chesapeake Bay Hall and the Fisheries Science Laboratory. New redundant fiber installations will result in a highly available, modern campus network infrastructure.
- Construct Concrete Pier
I Floor Plan I
The project replaces two damaged wooden piers (Oyster Pier and Ferry Pier) with a new concrete pier on the VIMS Gloucester Point shoreline. This pier will contain pumps and intake lines to provide 800 gallons per minute of treated seawater. A concrete pier will ensure that VIMS' seawater supply is safe from most hurricane force storms. The elevation of the pier will be set at 10.5 feet above mean lower low water. A location for the pier has been chosen based on a report from the A/E. Geotechnical work is complete. A Design-Build team has been selected. Construction is planned to be complete in March 2009.
- Electrical Upgrades, Chesapeake Bay Hall
This project involves upgrading the electrical distribution system at Chesapeake Bay Hall. The building's present electrical system does not provide the type of clean power needed by some of the sensitive electronic lab equipment and instrumentation used in modern research. The project will install transient voltage surge suppression and other improvements to the grounding system, the neutrals, branch circuiting balancing, power quality monitoring and installation of a central UPS system for critical emergency power loads. The equipment matrices inventorying the lab equipment by room was completed by VIMS in February 2008. The A/E is validating the equipment matrices through field work and is currently working on the design.
- Maury Hall Renovation
This project will be supported by the raising of private funds to renovate a 50-year old 6,400 square foot outdated laboratory into functional meeting and conference space for the campus. Planning for the project is on hold until sufficient funds have been raised.
- Research Storage Facility
The project involves the construction of a 4,600 square foot facility that is needed to secure research equipment and instruments that are currently stored outdoors. The project is currently on hold, but will begin planning as soon as we reach final completion of Andrews Hall.
- Miscellaneous Projects
- The following maintenance reserve projects are active:
- Planning
Structural Repairs, Hoxton Hall
- Complete - construction bids on hold.
Various Roof Replacements
- Under Construction
Replacement of HVAC compressors for Chesapeake Bay Hall South Wing. Replacement of Chesapeake Bay Hall roof-top condensers to start soon:
1. support frames for the evaporative condensers is out on bid. Bids due April 21st.
2. installation of evaporative condensers is out on bid. Bids due May 2nd.
3. evaporative condensers purchased on emergency purchase order. Delivery due Mid May.
|